Final Balcony Payment


Subject: Final Balcony Payment
From: Stankos, Brian (bstankos@CANNONDESIGN.COM)
Date: Wed Jun 18 2008 - 13:30:34 CDT


The Board of Directors is pleased to announce that the balcony project
is complete, with the exception of a few punchlist items. Alpine will
be on site on this Saturday and next Saturday to complete the punchlist.
The project was completed for less than the original budget of $750 per
balcony. The final cost was $701.25 per balcony.

 

The remaining balcony payment of $201.25 per balcony will be due from
residents on July 14th, 2008. A memo from First Properties will be
issued regarding the final payment as a reminder. Please note that the
final payment should be submitted as a check; direct debit can only
deduct assessments. Also, late fees will begin to incur after 7/14, so
make sure you submit payment by that date to avoid any fees.

 

Thanks for your patience during the construction.



This archive was generated by hypermail 2b28 : Mon Jul 27 2009 - 12:45:42 CDT